:: Schedule

Anticipated Construction Milestones

 Contract award  September 28 2006
Construction begins:
 
  Moore Drive preliminary earthworks and services relocation  November, 2006
  Hodges Drive to Shenton Avenue  January 2007
  Moore Drive closes  12 February 2007
  Shenton Avenue to Burns Beach Road  February 2007
  Rail tunnel  March 2007
  Winton Road footbridge  April 2007
  Shenton Avenue bridge  July 2007
   
Construction completed:
 
  Moore Drive reopens  21 October 2007
  Portmarnock Road Footbridge  21 October 2007
  Shenton Avenue bridge  July 2008
  Railworks  March 2008
  Hodges Drive bridge  April 2008
  Hodges Drive to Shenton Avenue roadworks  March 2008
  Shenton Avenue to Burns Beach Road roadworks  August 2008

 