| Contract award |
September 28 2006 |
Construction begins:
|
|
| Moore Drive preliminary earthworks and services relocation |
November, 2006 |
| Hodges Drive to Shenton Avenue |
January 2007 |
| Moore Drive closes |
12 February 2007
|
| Shenton Avenue to Burns Beach Road |
February 2007 |
| Rail tunnel |
March 2007 |
| Winton Road footbridge |
April 2007
|
| Shenton Avenue bridge |
July 2007
|
| |
|
Construction completed:
|
|
| Moore Drive reopens |
21 October 2007 |
| Portmarnock Road Footbridge |
21 October 2007
|
| Shenton Avenue bridge |
July 2008
|
| Railworks |
March 2008
|
| Hodges Drive bridge |
April 2008
|
| Hodges Drive to Shenton Avenue roadworks |
March 2008
|
| Shenton Avenue to Burns Beach Road roadworks |
August 2008
|